Watts acted as Project Managers for the refurbishment of the second and third floors of Aldwych House. On this occasion, we offered the client a one-stop service, covering not only project management, but also architecture, mechanical and electrical engineering, quantity surveying and structural engineering. We also instigated a separate stripping-out contract, which allowed tenderers for the refurbishment to price the works more accurately, thereby reducing the risk to co-owners of unforeseen variations.
The brief included stripping-out the previous tenant's fixtures and fittings, renewal of all services, construction of new toilets and complete refurbishment of the offices. The contract period was only 25-weeks but the project was completed within this period and without an increase in the contract sum.
|
|
|